Formulas used
- Holding cost per unit (H) = Unit cost × Holding cost %
- EOQ = √(2 × D × S ÷ H), where D is yearly demand and S is cost per order
- Orders per year = D ÷ EOQ
- Reorder point = (D ÷ 365) × Lead time days + Safety stock
Example
You sell 12,000 units a year. Each order costs ₹1,500 to place and receive, and holding one ₹100 unit for a year costs 20% (₹20). EOQ is about 1,342 units: roughly 9 orders a year, one every 41 days. With a 7-day lead time and 100 units of safety stock, reorder at about 330 units.
Frequently asked questions
What is EOQ?
Economic Order Quantity is the order size that keeps your total cost of ordering and storing stock as low as possible. Order too often and ordering costs pile up; order too much and storage costs do.
How is EOQ calculated?
EOQ = √(2 × Annual demand × Cost per order ÷ Holding cost per unit per year). At 12,000 units a year, ₹1,500 per order and ₹20 holding cost, EOQ is about 1,342 units.
What is holding cost?
The yearly cost of keeping one unit in stock: storage space, insurance, damage, theft, and the cash tied up. It is often 15–30% of the unit cost a year.
What is the reorder point?
The stock level at which you should place the next order so it arrives before you run out. Reorder point = Daily demand × Lead time + Safety stock.
Is my data saved or shared?
Your numbers are saved only in your own browser so they are there when you come back. Nothing is sent to Hire Arrive's servers.